Clay Surfacing

Highway No.47, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$51,775
Federal share25%

of $207.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2007
20082009
Built

Approved 7 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jul 24, 2007(actual)
Construction end
Jan 26, 2009(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2007
  • Construction end2 months earlyforecast Mar 31, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 16788 in the federal list. How to read these figures.