Schedule

Announced and approvedApr 13, 2007
2007
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Leroy
Construction start
Dec 20, 2006(actual)
Construction end
Oct 26, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end5 months earlyforecast Mar 31, 2008