Drinking Water Treatment Systems
Federal contribution
$250,000
Federal share17%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 5, 2007
2007200820092010
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Birch Hills
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Mar 23, 2010(actual)
Also in Birch Hills