Bedford Highway Bikeway: Phase 2
Federal contribution
$117,500
Federal share29%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 2, 2007
200720082009
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional Municipality of Halifax
- Construction start
- Jan 22, 2007(actual)
- Construction end
- Jul 31, 2009(actual)
Against the original forecast
- Construction start14 months lateforecast Nov 24, 2005
- Construction end4 months lateforecast Mar 31, 2009
Also in Halifax