Bedford Highway Bikeway: Phase 2

Halifax, Nova Scotia

completeActive TransportationMRIF
Federal contribution
$117,500
Federal share29%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 2, 2007
200720082009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 22, 2007(actual)
Construction end
Jul 31, 2009(actual)

Against the original forecast

  • Construction start14 months lateforecast Nov 24, 2005
  • Construction end4 months lateforecast Mar 31, 2009

Also in Halifax