Water Treatment Plant Upgrade
Federal contribution
$61,525
Federal share25%
of $246.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 3, 2007
2007200820092010
Built
Approved 3 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Rural Municipality of Frenchman Butte
- Construction start
- Dec 20, 2006(actual)
- Construction end
- Sep 7, 2010(actual)
Against the original forecast
- Construction end19 months earlyforecast Mar 31, 2012
Also in Frenchman Butte