Back to projects

Road Construction

Browning No. 34, Saskatchewan

completeHighways and RoadsMRIF
Federal contribution
$110,600
Federal share25%

of $442.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 5, 2007
2007
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Dec 20, 2006(actual)
Construction end
Oct 4, 2007(actual)

Against the original forecast

  • Construction start3 months earlyforecast Apr 1, 2007
  • Construction end6 months earlyforecast Mar 31, 2008

Also in Browning No. 34