Replacement of Sewage Lift Station - Argentia Management Authority

Argentia, Newfoundland and Labrador

completeWastewaterMRIF
Federal contribution
$63,528
Federal share33%

of $190.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20082010201220142016
Built

Approved 8.5 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Placentia
Construction start
Oct 21, 2008(actual)
Construction end
Jun 29, 2009(actual)

Against the original forecast

  • Construction start14 months lateforecast Sep 1, 2007
  • Construction end14 months lateforecast May 1, 2008

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17011 in the federal list. How to read these figures.