Network of drinking water pipes, sewer pipes, and sewage interception - Phase 2
Federal contribution
$1.3M
$1,263,642
Federal share32%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 26, 2010
2009201020112012
Built
Approved 2.3 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of L'Isle-Verte
- Construction start
- Jun 1, 2010(actual)
- Construction end
- Dec 31, 2011(actual)