Gjoa Haven Community Centre

Gjoa Haven, Nunavut

completeRecreationMRIF
Federal contribution
$2.5M
$2,475,000
Federal share45%

of $5.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
20082010201220142016
Built

Approved 7.9 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Government of Nunavut
Construction start
Apr 23, 2008(actual)
Construction end
Oct 1, 2010(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 1, 2007
  • Construction end18 months lateforecast Mar 31, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17059 in the federal list. How to read these figures.