Major water infrastructure upgrades in Saint-Antoine-Abbé sector of Franklin
Federal contribution
$2.3M
$2,347,741
Federal share44%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 14, 2009
200820092010201120122013
Built
Approved 2.4 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Franklin
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Dec 31, 2012(actual)
Against the original forecast
- Construction start11 months earlyforecast Aug 9, 2010
- Construction end9 months lateforecast Mar 31, 2012
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17086 in the federal list. How to read these figures.