Chemainus/Crofton STP Biosolids Processing Facility

Chemainus, British Columbia

completeWastewaterMRIF
Federal contribution
$1.5M
$1,500,000
Federal share33%

of $4.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 7, 2007
20082009201020112012
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
District of North Cowichan
Construction start
Sep 4, 2007(actual)
Construction end
Mar 31, 2012(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 21, 2007

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17171 in the federal list. How to read these figures.