Back to projects

Fraser-Fort George - Summit Lake Sewer System

Summit Lake, British Columbia

completeWastewaterMRIF
Federal contribution
$591,925
Federal share24%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 18, 2007
200820092010201120122013
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Sep 4, 2007(actual)
Construction end
Mar 31, 2013(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 21, 2007
  • Construction end12 months lateforecast Mar 31, 2012

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17237 in the federal list. How to read these figures.