South Huron Asset Management
Federal contribution
$4,863
Federal share33%
of $14.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 7, 2007
200720082009
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of South Huron
- Construction start
- Jun 15, 2007(actual)
- Construction end
- Feb 27, 2009(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Mar 31, 2009