Back to projects

Salmon Arm - 20/21 Street NE & Trans-Canada Highway Interchange

Salmon Arm, British Columbia

completeHighways and RoadsMRIF
Federal contribution
$1.0M
$1,000,000
Federal share20%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 7, 2008
2008200920102011
Built

Approved 6 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Salmon Arm
Construction start
Sep 4, 2007(actual)
Construction end
Mar 31, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 21, 2007

Also in Salmon Arm