Back to projects

Township of Laird Asset Management

Echo Bay, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,688
Federal share33%

of $11.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 7, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of Laird
Construction start
Aug 1, 2007(actual)
Construction end
Mar 31, 2009(actual)

Also in Echo Bay