Saturna Island - Lyall Harbour / Boot Cove Water Treatment System Upgrade
Saturna Island, British Columbia
Federal contribution
$372,042
Federal share29%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 23, 2008
200820092010201120122013
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Regional District of Capital
- Construction start
- Dec 12, 2007(actual)
- Construction end
- Mar 31, 2013(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 19, 2007
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17536 in the federal list. How to read these figures.