Whitchurch-Stouffville Asset Management
Federal contribution
$6,629
Federal share33%
of $19.9K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedMay 7, 2007
20072008
Built
Approved 5 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Whitchurch-Stouffville
- Construction start
- May 15, 2007(actual)
- Construction end
- Oct 20, 2008(actual)
Against the original forecast
- Construction end10 months lateforecast Dec 20, 2007