Slocan - Environmental Energy Improvement
Federal contribution
$57,356
Federal share28%
of $204.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 19, 2008
20082009201020112012
Built
Approved 5 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Village of Slocan
- Construction start
- Dec 12, 2007(actual)
- Construction end
- Mar 31, 2012(actual)
Against the original forecast
- Construction start3 weeks lateforecast Nov 19, 2007