West Nipissing Asset Management

Sturgeon Falls, Ontario

completeCapacity BuildingMRIF
Federal contribution
$7,153
Federal share33%

of $21.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 7, 2007
20072008
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 15, 2007(actual)
Construction end
Jul 9, 2008(actual)

Against the original forecast

  • Construction end6 months earlyforecast Dec 31, 2008