Back to projects

Asset Management

Cayuga, Ontario

completeCapacity BuildingMRIF
Federal contribution
$16,267
Federal share33%

of $48.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedMay 24, 2007
2007200820092010
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
County of Haldimand
Construction start
Jun 1, 2007(actual)
Construction end
Mar 23, 2010(actual)

Against the original forecast

  • Construction end15 months lateforecast Dec 31, 2008

Also in Cayuga

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17785 in the federal list. How to read these figures.