Back to projects

Cardigan Ballfield Complex Upgrades

Cardigan, Prince Edward Island

completeSportMRIF
Federal contribution
$55,500
Federal share33%

of $166.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 20, 2007
20082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Community of Cardigan
Construction start
May 1, 2007(actual)
Construction end
Mar 31, 2009(actual)

Against the original forecast

  • Construction end17 months lateforecast Oct 31, 2007

Also in Cardigan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17797 in the federal list. How to read these figures.