Extension of the water supply and sewer system in the Chevrons-Dionne district
Federal contribution
$78,665
Federal share30%
of $265.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 15, 2008
2008200920102011
Built
Approved 2 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Saint-Pacôme
- Construction start
- Apr 1, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Also in Saint-Pacôme