Back to projects

Extension of the water supply and sewer system in the Chevrons-Dionne district

Saint-Pacôme, Quebec

completeWastewaterMRIF
Federal contribution
$78,665
Federal share30%

of $265.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 15, 2008
2008200920102011
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 1, 2009(actual)
Construction end
Mar 31, 2011(actual)

Also in Saint-Pacôme

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17822 in the federal list. How to read these figures.