The City of Brantford - Asset Management
Federal contribution
$28,840
Federal share33%
of $86.5K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 26, 2007
20072008
Built
Approved 7 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Brantford
- Construction start
- Jun 30, 2007(actual)
- Construction end
- Sep 15, 2008(actual)
Against the original forecast
- Construction end4 months earlyforecast Dec 31, 2008
Also in Brantford
- Laurier Brantford YMCA Athletics and Recreation Complex$16.7M
- Construction of Wayne Gretsky Centre Four-Pad Arena$13.0M
- Upgrade of the Water Treatment Plant$5.4M
- Enclosing Open Concept Classrooms; HVAC; Water filling Station; Hallway door hold open devices; Entrance door security access$4.7M
- Grand Riverview$4.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17922 in the federal list. How to read these figures.