Back to projects

Town of Minto Asset Management

Harriston, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,590
Federal share33%

of $13.8K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008200920102011
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Minto
Construction start
Jun 18, 2007(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction end2 years lateforecast Dec 31, 2008

Also in Harriston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17935 in the federal list. How to read these figures.