Mississauga Bus Rapid Transit - Missisauga Segments
Federal contribution
$59.0M
$59,000,000
Federal share33%
of $177.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 6, 2007
2007201020132016
Built
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- City of Mississauga and Greater Toronto Transit Authority
- Construction start
- Nov 1, 2010(actual)
- Construction end
- Apr 15, 2018(actual)
Against the original forecast
- Construction end6 months lateforecast Sep 30, 2017
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 17958 in the federal list. How to read these figures.