Township of East Ferris Asset Management

Corbeil, Ontario

completeCapacity BuildingMRIF
Federal contribution
$4,651
Federal share33%

of $14.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
2007200820092010
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Township of East Ferris
Construction start
Jun 18, 2007(actual)
Construction end
Dec 4, 2009(actual)

Against the original forecast

  • Construction end11 months lateforecast Dec 31, 2008