Township of East Ferris Asset Management
Federal contribution
$4,651
Federal share33%
of $14.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
2007200820092010
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of East Ferris
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Dec 4, 2009(actual)
Against the original forecast
- Construction end11 months lateforecast Dec 31, 2008
Also in Corbeil