Back to projects

Village of Oil Springs - Asset Management

Oil Springs, Ontario

completeCapacity BuildingMRIF
Federal contribution
$3,499
Federal share33%

of $10.5K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedDec 6, 2006
ApprovedJun 18, 2007
200720082009
Built

Approved 6 months after the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Oil Springs
Construction start
Jun 18, 2007(actual)
Construction end
Jan 12, 2009(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2009

Also in Oil Springs

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18034 in the federal list. How to read these figures.