Front of Yonge - Asset Management Plan
Federal contribution
$3,776
Federal share33%
of $11.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Front of Yonge
- Construction start
- Aug 21, 2007(actual)
- Construction end
- Aug 24, 2008(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 15, 2007
- Construction end2 months lateforecast Jun 15, 2008