Township of Tarbutt & Tarbutt Additional Asset Management
Tarbutt and Tarbutt Additional, Ontario
Federal contribution
$3,525
Federal share33%
of $10.6K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of Tarbutt and Tarbutt Additional
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Jan 30, 2008(actual)
Against the original forecast
- Construction end5 months earlyforecast Jun 15, 2008
Also in Tarbutt and Tarbutt Additional
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18149 in the federal list. How to read these figures.