Township of South Algonquin Asset Management
Federal contribution
$3,764
Federal share33%
of $11.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedDec 6, 2006
ApprovedJun 18, 2007
20072008200920102011
Built
Approved 6 months after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Township of South Algonquin
- Construction start
- Jun 18, 2007(actual)
- Construction end
- Mar 31, 2011(actual)