Water and sewer mains repairs, Patry and Taché Streets

Saint-Pascal, Quebec

completeDrinking WaterMRIF
Federal contribution
$902,183
Federal share28%

of $3.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.6 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Saint-Pascal
Construction start
Jul 13, 2009(actual)
Construction end
Mar 31, 2010(actual)

Also in Saint-Pascal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18246 in the federal list. How to read these figures.