Water and sewer mains repairs, Patry and Taché Streets
Federal contribution
$902,183
Federal share28%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.6 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Saint-Pascal
- Construction start
- Jul 13, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Also in Saint-Pascal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18246 in the federal list. How to read these figures.