Improvement of Aspen Drive in the Hamlet of Zama City
Federal contribution
$260,000
Federal share24%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 1, 2008
2008
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipal District of Mackenzie No. 23
- Construction start
- Mar 22, 2008(actual)
- Construction end
- Sep 20, 2008(actual)