Stony Plain Exhibition Park Revitalization

Stony Plain, Alberta

completeTourismMRIF
Federal contribution
$1.2M
$1,227,198
Federal share28%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 2, 2007
20082009201020112012
Built

Approved 8 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Stony Plain
Construction start
Feb 1, 2009(actual)
Construction end
Nov 30, 2011(actual)

Against the original forecast

  • Construction end20 months lateforecast Mar 31, 2010

Also in Stony Plain

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18357 in the federal list. How to read these figures.