North Access Road & South Access Road Overlay

Gift Lake Metis Settlement, Alberta

completeHighways and RoadsMRIF
Federal contribution
$1.2M
$1,152,468
Federal share33%

of $3.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 20, 2008
200820092010
Built

Approved 7 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Gift Lake Metis Settlement
Construction start
Oct 15, 2008(actual)
Construction end
Mar 9, 2010(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2008
  • Construction end4 months lateforecast Oct 30, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18430 in the federal list. How to read these figures.