Sanitary Trunk Gravity Mains
Federal contribution
$376,233
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 1, 2008
2008200920102011
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of High Level
- Construction start
- Jul 10, 2008(actual)
- Construction end
- Mar 9, 2011(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2008
- Construction end23 months lateforecast Mar 31, 2009
Also in High Level