Back to projects

Construction of a new well in East Hereford

East Hereford, Quebec

completeDrinking WaterMRIF
Federal contribution
$91,000
Federal share21%

of $441.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 14, 2008
200920102011
Built

Approved 4 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Apr 1, 2009(actual)
Construction end
Mar 31, 2011(actual)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18633 in the federal list. How to read these figures.