Re-building Alida Pool

Alida, Saskatchewan

completeRecreationMRIF
Federal contribution
$55,851
Federal share25%

of $223.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 21, 2008
200820092010
Built

Approved 5 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Village of Alida
Construction start
Dec 14, 2007(actual)
Construction end
Dec 15, 2009(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2010

Also in Alida