Water and sewer infrastructure to serve housing development near Mont-Edouard
Federal contribution
$595,047
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 24, 2009
200920102011
Built
Approved 4 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of L'Anse-Saint-Jean
- Construction start
- Jan 12, 2009(actual)
- Construction end
- Feb 1, 2011(actual)
Against the original forecast
- Construction start7 weeks earlyforecast Mar 1, 2009
- Construction end5 weeks lateforecast Dec 31, 2010
Also in L'Anse-Saint-Jean
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 18905 in the federal list. How to read these figures.