Upgrading of drinking water production plant, City of Beauharnois - Melocheville sector
Federal contribution
$225,000
Federal share6%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2009201120132015
Built
Approved 7.5 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Beauharnois
- Construction start
- Nov 1, 2008(actual)
- Construction end
- Dec 31, 2012(actual)
Against the original forecast
- Construction end9 months lateforecast Mar 31, 2012
Also in Beauharnois
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19396 in the federal list. How to read these figures.