Little Narrows Water System, Phase 4 - Reservoir

Mackinnon's Harbour, Nova Scotia

completeDrinking WaterMRIF
Federal contribution
$60,739
Federal share20%

of $300.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 13, 2008
2009
Built

Approved 2 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jan 28, 2008(actual)
Construction end
Oct 23, 2009(actual)

Against the original forecast

  • Construction start2.2 years lateforecast Nov 25, 2005
  • Construction end5 months earlyforecast Mar 31, 2010

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19470 in the federal list. How to read these figures.