Replacement of Cast Iron Watermains in Dunnville
Federal contribution
$1.3M
$1,265,249
Federal share33%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 9, 2008
20082009201020112012
Built
Approved 7 weeks after the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Haldimand
- Construction start
- Mar 26, 2008(actual)
- Construction end
- Dec 31, 2011(actual)
Against the original forecast
- Construction end14 months lateforecast Oct 31, 2010
Also in Dunnville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19709 in the federal list. How to read these figures.