Drinking water distribution and wastewater collection, Highway 143

Val-Joli, Quebec

completeWastewaterMRIF
Federal contribution
$229,900
Federal share19%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2009201120132015
Built

Approved 7.3 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Municipality of Val-Joli
Construction start
May 1, 2009(actual)
Construction end
Jul 15, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast Jan 1, 2009

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19860 in the federal list. How to read these figures.