Water System Improvements

Burnt Islands, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$121,749
Federal share33%

of $368.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.7 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Burnt Islands
Construction start
Jun 30, 2009(actual)
Construction end
Nov 9, 2009(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast Aug 2, 2009
  • Construction end4 months earlyforecast Feb 28, 2010

Also in Burnt Islands

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 19970 in the federal list. How to read these figures.