Reporting of Tangible Capital Assets

Saskatchewan, Saskatchewan

completeCapacity BuildingMRIF
Federal contribution
$221,543
Federal share50%

of $443.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 6, 2008
20092010201120122013
Built

Approved 4 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Sarm/Suma/Sanc
Construction start
May 7, 2008(actual)
Construction end
Mar 31, 2013(actual)