Water System Upgrades
Federal contribution
$577,252
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 14, 2009
20092011201320152017
Built
Approved 3 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Perth-Andover
- Construction start
- Oct 15, 2009(actual)
- Construction end
- Nov 25, 2016(actual)
Against the original forecast
- Construction end15 months lateforecast Aug 31, 2015
Also in Perth-Andover
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22033 in the federal list. How to read these figures.