Water System Improvements

Buchan's Junction, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$166,648
Federal share33%

of $499.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Construction start
Jun 25, 2009(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction end13 months lateforecast Sep 30, 2009