Hamlet of Kronau-Sewage Pumping Station Upgrade & Expansion
Federal contribution
$104,348
Federal share33%
of $313.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
20092010201120122013
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Rural Municipality of Lajord
- Construction start
- Sep 28, 2009(actual)
- Construction end
- Mar 15, 2013(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2009
- Construction end13 months earlyforecast Mar 31, 2014
Also in Lajord No. 128
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22072 in the federal list. How to read these figures.