Water Supply, Storage and Distribution Infrastructure Upgrades
Federal contribution
$1.5M
$1,475,708
Federal share33%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 20, 2009
201020112012
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of New Maryland
- Construction start
- Aug 1, 2009(actual)
- Construction end
- Mar 9, 2012(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2009
- Construction end18 months earlyforecast Aug 30, 2013
Also in New Maryland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22104 in the federal list. How to read these figures.