Back to projects

Water Supply, Storage and Distribution Infrastructure Upgrades

New Maryland, New Brunswick

completeDrinking WaterCC
Federal contribution
$1.5M
$1,475,708
Federal share33%

of $4.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 20, 2009
201020112012
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of New Maryland
Construction start
Aug 1, 2009(actual)
Construction end
Mar 9, 2012(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2009
  • Construction end18 months earlyforecast Aug 30, 2013

Also in New Maryland