Water collection and treatment work
Federal contribution
$180,000
Federal share40%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2009
2009201020112012
Built
Approved 12 months before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Municipality of Lac-Saint-Paul
- Construction start
- Oct 1, 2009(actual)
- Construction end
- Mar 31, 2012(actual)