Asphalt Paving - Local Roads
Federal contribution
$384,115
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 20, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Rosthern
- Construction start
- Aug 13, 2009(actual)
- Construction end
- May 21, 2010(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2009
- Construction end22 months earlyforecast Mar 31, 2012
Also in Rosthern
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22138 in the federal list. How to read these figures.